August 14, 2024
2:00 p.m. — All campus buildings have been cleared to reopen Thursday morning, Aug. 15. Repairs and testing have been completed, and systems are currently being brought back online.
11:00 a.m. — Repairs of the cracked water line are in progress, and testing will begin soon. We will continue to provide updates here as the work progresses and we know when a return to normal campus operations will be possible.
August 13, 2024
Due to a broken water line, CalArts’ main campus is closed to all but essential employees until further notice.
Please continue to check this page for updates.
Additional Information
On Tuesday afternoon, Aug. 13, a sudden crack in a primary water pipe feeding the Chouinard residence hall occurred that necessitated shutting off all water to the main campus at approximately 4:00 pm.
Water and air-conditioning will remain shut off until the affected water line can be capped.
The shut-off affects ALL water to the main campus, including the Chouinard and Ahmanson residence halls. This includes restrooms, sinks, showers, drinking fountains, etc. It also requires turning off the HVAC (air-conditioning) system.
Vista Village is NOT affected, and is operating normally.
We regret the inconvenience, and appreciate your patience and understanding as our Facilities Management team works to make repairs.